Both tracks of the new Portal North Bridge were in service Monday, November 16, ending a five-week stretch of reduced rail service in northern New Jersey. NJ Transit and Amtrak trains crossed the Hackensack River on the replacement bridge while officials marked the change at a ribbon-cutting in Kearny. The two railroads confirmed that the 116-year-old span had been retired from train service. Colleen Wilson of NorthJersey.com reported seeing both Amtrak and NJ Transit trains pass during the ceremony.
The old crossing was a swing bridge. It had to rotate out of the way for tall boats, and trains had to wait until it turned back and was ready for rail traffic. The moving bridge sometimes got stuck, adding delays to a route used by commuter trains into New York as well as intercity trains. The new bridge stands about 50 feet above the water, roughly twice the previous clearance, and is fixed in place. Boats that can pass under it no longer require the bridge to move.
What changes for riders
For many riders, the most immediate change was the return of their customary route. During the last part of construction, weekday Midtown Direct trains on the Morristown Line, Gladstone Branch and Montclair-Boonton Line went to Hoboken instead of New York Penn Station, CBS New York reported. Anyone continuing to Manhattan had to make another connection, such as to PATH, a ferry or a bus. Some riders on the Northeast Corridor and North Jersey Coast Line had fewer trains to choose from, too. Amtrak and NJ Transit said the temporary weekday diversions ended with the return of regular weekday service on November 16.
The new bridge had already been carrying trains since the first track went into use in March. That work was only half of the transfer. The old bridge still carried traffic while service was split between the two structures. To finish the job, crews started moving the second track on October 9. Trains had to share a single track on the busy stretch between Newark and Secaucus while work went on, CBS reported. The November milestone was the first Monday with both tracks in service on the new bridge, not the first time a passenger train had crossed it.
NorthJersey.com reported that about 450 trains use this part of the corridor each day. Building alongside a crossing that busy meant the old bridge could not simply be shut down for the duration of construction. Crews brought three large steel arches to the project by barge, the outlet reported, while railway traffic continued to use the old crossing. The reported $2.3 billion price describes the overall project, not an individual bridge component.
The work was funded by the U.S. Department of Transportation, New Jersey, New York and Amtrak. The main construction contract, awarded in 2021 for about $1.56 billion, was the largest the transit agency had awarded, the joint release said. A separate federal grant agreement announced that year committed $766.5 million toward construction, according to the railroads.
The original crossing had been in operation since 1910. It stood between Kearny and Secaucus, on an approach that carries local and longer-distance travelers into Manhattan. Its retirement from service and its removal are separate steps. NorthJersey.com reported demolition of the old bridge had begun; the opening does not mean the old structure had already disappeared. The new span is part of the broader Gateway Program, but it is not the new tunnel under the Hudson. That separate work remains unfinished.
The fixed crossing removes a specific reason trains could stop or run late: the old bridge opening for maritime traffic or failing to return to its rail position. It does not establish how much time riders will save, and a train can still be delayed elsewhere on the route. The change commuters can already use is the return of their trains. After weeks of diversions and fewer departures, regular weekday service is back on this approach, and trains now cross the Hackensack without a movable span in the way.